- Installation of new Maerz Vertical Kiln.
- Installation (2) new 12.5kV primary services with (2) 480 volt 3000amp Services.
- Installation of new Motor Control Centers for the control of new and existing equipment.
- Installation of new PLCs for the integration of existing and new controls.
- Relocation of existing Feeders and control for the installation of new equipment.